Project Plan - PantherLink Project

Phase One
Product selection, completed February 2007


Phase Two
October 2007 -- May 2008


Goal: To migrate approximately 4 terabytes of e-mail data from PantherMail to PantherLink

Completed as of March 27, 2008:

  • Approximately 50 faculty, staff and student test accounts running
  • Development and test environment in place
  • Plans underway to design and build production environment
  • LDAP authentication functionality confirmed in new environment
  • Configure servers
  • Assess the impact of the migration on the current e-mail environment
  • Develop data back-up strategies
  • Draft Phase 2 communications plan

Technical tasks to be completed:

  • Investigate ways to integrate UWM brand into application
  • Develop migration Help Desk documentation
  • Migrate user accounts from PantherMail to the PantherLink infrastructure (with no interface change)

Client issues to be investigated:

  • PantherCal: Ascertain the impact of the migration on PantherCal
  • GroupWise and Exchange accounts: Address the migration of accounts utilizing GroupWise and Exchange
  • Training: Formulate content for campuswide training materials
  • myUWM portal: Prototype PantherLink functionality in the myUWM portal

Phase Three