Environmental Project Log: Kenilworth DFD #002B2Q


Kenilworth Building Status as of April 30, 2002.

Kenilworth Building View of furnace demolition on April 30, 2002.

Kenilworth Building Project status on May 3, 2002.

Kenilworth Building Project status on May 7, 2002. View of furnace floor/base. The yellow refractory bricks and sand were asbestos-free; however, there was still some presumed asbestos insulation and debris in this remaining demolition material. The furnace floor was unknown (sample #20513K98). Project completion is expected by May 17, 2002, pending other "priority" projects at UWM.

Go to Image Page 1 or Image Page 2 or Image Page 4 or Image Page 5 or Image Page 6

Please see the Kenilworth Index Page and Project Log for additional information.



Return to Asbestos Management Program Home Page