Milestone Responsible Party Target Completion Date Status
Campus Announcement Communication Subteam June 2013
Complete
Open Sessions
Communication Subteam
July 2013
Complete
Surveys Communication Subteam July 2013
Complete
Plugin Collection and Catalog
Plugins & Extensibility Subteam
Fall 2013
In Progress
Working Prototype
Platform Subteam
September 16, 2013
Complete
Alpha Phase Starts
All Teams
October 7, 2013
Complete
Alpha Phase Completed
All Teams
November 6, 2013
Complete
Web ID Themes
Themes Subteam
October 2013
Complete
Beta Phase Starts
All Teams
November 15, 2013
In Progress
Beta Phase Completed
All Teams
First Quarter 2014
In Progress
Campus Funding Secured
Project Management Subteam
Fall 2013
In Progress
Advisory Group Formation
Project Management Subteam
Fall 2013
In Progress
Learning Services Available
Learning & Professional Development Subteam
First Quarter 2014
In Progress
Service Management and Support Structure Ready
Service Management & Operational Support Subteam
First Quarter 2014
In Progress
General Availability
Platform Subteam First Quarter 2014
In Queue